How to calculate fully loaded labor burden for a 1–5 person trade crew
A wage is only the starting point. Payroll taxes, insurance, vehicles, paid time off, and unbilled hours all sit on top of it. This walkthrough shows one way to turn those pieces into a cost per billable hour — the number you can enter as a labor cost, not a billed rate, in a job quote.
What “loaded labor burden” means here
Loaded labor burden is the full annual cost of having someone on the crew, divided by the hours you can actually bill. It is a cost-accounting exercise, not a selling price. The job quote calculator labels this as “labor rate — cost per hour, not the billed rate.” After you have it, you still add materials, any remaining overhead, and a target margin.
The method is the same for a solo operator or a five-person crew. A worked example for three employees is below, with shared costs split evenly. If your people are not employees, the tax and insurance categories change; that is a question for a professional, not something this page decides.
The pieces that usually get left out
Base wage
Start with the hourly wage you actually pay, then annualize it over the hours you pay in a year. In the example, that is 40 hours a week for 52 weeks, or 2,080 paid hours, including paid time off. If someone is paid only for hours worked, use that figure instead and keep time off visible in a later step.
Payroll tax concepts (FICA, FUTA, SUTA)
Employers often pay a share of Social Security and Medicare (commonly discussed together as FICA), plus federal and state unemployment taxes (often abbreviated FUTA and SUTA or SUI). These are separate from the amounts withheld from a paycheck. Rates, wage bases, and credits vary and change. Unemployment taxes are often calculated only on a portion of wages, not on every dollar of payroll — so applying a unemployment percentage to all wages can overstate the cost.
The example uses 7.65% of annual wages as a stand-in for the employer FICA share, $42 as a stand-in for federal unemployment tax (0.6% × a $7,000 wage base), and $270 as a stand-in for state unemployment tax (2.7% × a $10,000 wage base). Those numbers are illustrations only. They are not official current rates and not a calculation of what any business owes.
Workers’ compensation
Workers’ compensation premiums depend on classification, state rules, claims history, and payroll. They are not a single national percentage. The example uses 4.5% of annual wages as a stand-in so you can see where the line item goes. Replace it with the premium you actually pay, converted to an annual amount.
Liability insurance allocation
A general liability policy is usually paid for the business, not for one person. To include it in labor burden, take the annual premium and allocate it across the crew — by headcount, by hours, or by another split you can explain. The example uses a $3,600 annual premium, split three ways, or $1,200 per person. If you already put this premium entirely into monthly overhead on the break-even jobs calculator, do not also load it into the labor rate, or you will count it twice.
Vehicles, fuel, and tools
Vans, fuel, maintenance, phones, and tools are easy to forget when a “labor rate” starts at the wage. The example allocates $12,000 a year for vehicles and fuel and $3,000 a year for tools and small equipment, split evenly across three people ($4,000 and $1,000 each). Use your own totals. If a cost belongs to one person or one truck, assign it there instead of splitting it.
Paid time off and holidays
If you pay for vacation and holidays, those hours cost money but do not go out on billable jobs. The annual cost does not change; it is simply spread over fewer working hours. In the example, each person has 10 holidays and 10 paid vacation days, or 160 hours, leaving 1,920 hours actually available to work.
Billable efficiency
Not every hour at work is billed. Drive time, parts runs, cleanup, quoting, admin, and unpaid callbacks all reduce the hours that can carry the annual cost. The example assumes 70% of hours at work are billable, so 1,920 × 0.70 = 1,344 billable hours per person. That 70% is an assumption for the example, not a benchmark or a recommended utilization rate. Use a percentage that matches how your days actually go.
A worked example: three-person crew
The crew in this example is a lead at $32 an hour, a technician at $24, and a helper at $20. Each is paid for 2,080 hours. Shared annual costs are $3,600 liability insurance, $12,000 vehicles and fuel, and $3,000 tools, or $18,600, split evenly at $6,200 per person. Again, every rate and premium below is a stand-in.
Step 1 — Hours
| Hour category | How it is calculated | Hours per person |
|---|---|---|
| Paid hours | 52 weeks × 40 hours | 2,080 |
| Paid time off | 20 days × 8 hours | 160 |
| Hours at work | 2,080 − 160 | 1,920 |
| Billable hours | 1,920 × 70% | 1,344 |
Step 2 — Annual cost for each person
| Line item | Lead ($32/hr) | Technician ($24/hr) | Helper ($20/hr) |
|---|---|---|---|
| Annual base wage | $66,560.00 | $49,920.00 | $41,600.00 |
| Employer FICA stand-in (7.65%) | $5,091.84 | $3,818.88 | $3,182.40 |
| FUTA stand-in | $42.00 | $42.00 | $42.00 |
| SUTA stand-in | $270.00 | $270.00 | $270.00 |
| Workers’ comp stand-in (4.5% of wage) | $2,995.20 | $2,246.40 | $1,872.00 |
| Allocated liability insurance | $1,200.00 | $1,200.00 | $1,200.00 |
| Allocated vehicles and fuel | $4,000.00 | $4,000.00 | $4,000.00 |
| Allocated tools | $1,000.00 | $1,000.00 | $1,000.00 |
| Total annual loaded cost | $81,159.04 | $62,497.28 | $53,166.40 |
Step 3 — Cost per hour
| Cost divided by | Lead | Technician | Helper |
|---|---|---|---|
| Paid hours (2,080) | $39.02 | $30.05 | $25.56 |
| Hours at work (1,920) | $42.27 | $32.55 | $27.69 |
| Billable hours (1,344) | $60.39 | $46.50 | $39.56 |
The useful figure for job costing is usually the last row: cost per billable hour. The lead’s $32 wage becomes $60.39 of cost once the stand-in burden and the unbilled hours are included. The three rates together are $146.45 for each hour the full crew is on a job. Across the crew, annual loaded cost is $196,822.72 over 4,032 billable hours, or $48.82 on average per person-hour.
If you price a job that needs the lead for two hours and the helper for two hours, use $60.39 and $39.56, not the $48.82 average. Averages hide crew mix.
Step 4 — Use the number in a quote, not as the quote
Enter the billable-hour cost in the labor-rate field of the job quote calculator, then add materials, overhead you have not already allocated, and a target margin. The quote is cost ÷ (1 − margin), which is not the same as adding a markup. The markup vs. margin calculator shows the difference. To see how many jobs a month cover shop overhead after these labor costs, use the break-even jobs calculator with realistic direct costs.
Common mistakes
Costing a job at the wage alone understates labor before any margin is applied. Counting the same insurance or vehicle payment once in the loaded rate and again as job overhead double-counts it. Applying an unemployment tax rate to all wages, when that tax is only due on a wage base, overstates the burden. And treating paid hours as billable hours spreads the annual cost over time that never appears on an invoice.
None of these figures is a recommended wage, premium, utilization rate, or billed price. Replace every stand-in with your own numbers before you rely on the result.
Questions
Is the loaded cost per billable hour the rate I should charge customers?
No. The loaded figure in this example is a cost, not a selling price. You would still add materials, any job-specific costs, overhead that was not already allocated, and a target margin. The job quote calculator is built for that next step. This page does not recommend a billed rate.
Do these payroll tax percentages apply to my business?
Not necessarily. The FICA, FUTA, and SUTA figures in the tables are illustration numbers used to show the steps. Actual rates, wage bases, credits, and who must pay them depend on your situation and change over time. Look up the current figures that apply to you, or ask a payroll professional or accountant. This is not a tax calculation and not tax advice.
Can I just multiply the wage by 1.3 or 1.5?
Some shops use a multiplier as a shortcut. A multiplier can hide a mix of taxes, insurance, vehicles, time off, and unbilled hours that does not match yours. Building the cost once, with your own numbers, makes the rate easier to update when a premium or a wage changes. A multiplier is not a substitute for your figures, and this page does not endorse a particular one.
What if I am a solo operator, or I have five people instead of three?
The steps are the same. A solo operator puts all shared costs — insurance, vehicles, tools — on one person. A five-person crew can split those shared costs by headcount, by hours, or by another allocation you choose. The example uses three people and an even split only to keep the arithmetic easy to follow.
Should the owner’s time be included?
If the owner works on jobs, leaving that time out makes the job look cheaper than it is. Many owner-operators enter a wage equivalent for the hours they work in the field so the loaded cost is visible. How you pay yourself is a separate question, and this page does not give tax or compensation advice.
Related guides and tools
For the difference between a trip fee and a diagnostic fee, see minimum service call fee vs. diagnostic fee. For how a written estimate differs from a quote, see estimate vs. quote vs. proposal. To keep a rate planner and job-cost sheet you can reuse, see the Job Quoting Kit — a $29 one-time workbook and PDF guide.
Open the job quote calculator See the Job Quoting Kit — $29
Educational guide only. Not financial, tax, payroll, legal, insurance, or business advice. The worked numbers are illustrations. No income, profit, or result is guaranteed.